Visualisation of the three AP1000 units of the Lubiatowo-Kopalino nuclear power plant

Nuclear power plant in Poland - what has been done and when it starts

In brief

Preparatory works on the site are already under way. First concrete is planned for 2028, unit 1 is to deliver power in 2036, and the contract with the contractor is still unsigned.

Last updated: 5 September 2026

What this project is

Poland’s first nuclear power plant is being built on the Baltic coast, in the Choczewo commune in Wejherowo county, on a site designated in the documents as “Lubiatowo-Kopalino”. A few dozen kilometres from Gdańsk, in a belt of dunes and pine forest, in a place that was studied for 4 years - from 2017 to 2021 - alongside the second candidate, Żarnowiec.

Illustrative visualisation of Poland’s first nuclear power plant at Lubiatowo-Kopalino - 3 AP1000 units on the Baltic shore
Illustrative visualisation of Poland’s first nuclear power plant. Source: Polskie Elektrownie Jądrowe.

The construction site - about 330 hectares - was handed over by PEJ to Bechtel on 5 August 2026. Three reactors will stand there: AP1000 - a Westinghouse design, generation III+, of about 1,250 MWe gross each. The investor is Polskie Elektrownie Jądrowe, wholly owned by the State Treasury. Design and construction are carried out by the consortium of Westinghouse and Bechtel. According to PEJ the 3 units will cover the demand of more than 12 million households.

The plant itself is only part of what is being built. Components that cannot travel by ordinary road have to reach Lubiatowo - hence the marine structure about a kilometre long being built beside the plant for unloading oversized cargo straight from the sea, for which the Maritime Office in Gdynia is responsible. Add to that a national road about 26 km long in two sections, the modernisation of railway lines 229 and 230 on three sections and an entirely new Choczewo - Steknica line with a stop at the plant, as well as a substation at Biebrowo with transmission lines on the PSE side.

GdańskSzczecinPoznańWrocławKrakówWarsawLubiatowo-KopalinoChoczewo communeWejherowo county
Location map of “Lubiatowo-Kopalino” - Choczewo commune, Wejherowo county, Pomeranian Voivodeship.

Position as at September 2026

First concrete
2028
Update of the Polish Nuclear Power Programme, 24 June 2026. President of PEJ, 25 June 2026: “even if this happens in early 2029” - with no change to the start-up date.
Previously: start of construction in 2026 (PPEJ 2020)
Operation of unit 1
2036
The date in force since December 2024, confirmed in the Programme update of 24 June 2026.
Previously: 2033 (PPEJ 2020)
Units 2 and 3
2037 · 2038
Update of the Polish Nuclear Power Programme, 24 June 2026.
Previously: 2035 i 2037 (PPEJ 2020)
EPC contract
unsigned
As at 5 August 2026. The Ministry of Energy on 22 July 2026: negotiations to be finalised by the end of the year.
Previously: negotiations to close by 30 June 2026

What has happened recently

  • Q3 2026 - earthworks have started on the site. The main earthworks contractor is Budimex; more than 200 people are working on the site.
  • 5 August 2026 - PEJ handed the construction site over to Bechtel, about 330 hectares at Lubiatowo-Kopalino.
  • 30 July 2026 - 6 Polish companies entered the third and final stage of qualification: manufacture of trial components and quality control against ASME NQA-1.
  • 22 July 2026 - the deputy minister of energy in the Senate: negotiation of the EPC contract with the Westinghouse - Bechtel consortium to be finalised by the end of 2026.
  • 1 July 2026 - the Pomeranian Voivode granted consent for the second stage of preparatory works.
  • 24 June 2026 - the Ministry of Energy published the full text of the updated Polish Nuclear Power Programme.
  • 8 May 2026 - PEJ received the opinion of the President of the Polish National Atomic Energy Agency (PAA) on the nuclear safety of the site.

Timeline

Each year expands when clicked. An entry is a date, one sentence and a link to the source.

2026
  • Q3 fact Earthworks began on the investment site. The main earthworks contractor is Budimex SA. Scope: site levelling, rebuilding and extension of drainage, about 16 km of temporary roads and about 6 km of drainage ditches. The works are scheduled between Q3 2026 and Q1 2029. Marek Woszczyk, President of the PEJ Management Board: “Over 200 people are already working on the investment site today”. From the press release of 5 August 2026. Polska Platforma Jądrowa
  • 2 September fact The amendment to the act on the preparation and delivery of investments in nuclear power facilities and accompanying investments entered into force. The act was passed on 3 July 2026 and published in the Journal of Laws on 18 August 2026. ISAP - Dz.U. 2026 poz. 1097
  • 5 August fact PEJ handed the construction site over to Bechtel - about 330 hectares at Lubiatowo-Kopalino. The president of PEJ, Marek Woszczyk: delivery of the contract is on schedule and the project is recording no delays. Ministerstwo Energii
  • 30 July fact 6 Polish companies - FAMAK, ZKS Ferrum, Mostostal Kielce, Mostostal Siedlce, Mostostal Kraków and Energomontaż-Północ Gdynia - began the third stage of qualification: manufacturing trial components and submitting them to quality control for conformity with ASME NQA-1. PEJ
  • 22 July fact Parliament adopted the amendment to the act on the preparation and delivery of investments in nuclear power facilities. The new provisions allow preliminary construction works to start earlier and the investment to be staged more widely. Ministerstwo Energii
  • 22 July date Deputy Minister of Energy Konrad Wojnarowski in the Senate: negotiation of the EPC contract with the Westinghouse - Bechtel consortium to be finalised by the end of 2026. Senat RP
  • 2 July fact Bechtel signed contracts with BARG M.B. Gdańsk (materials laboratory, a two-year contract) and with MSA Security (security of the construction site). Zielona Gospodarka
  • 1 July fact The Pomeranian Voivode granted consent for the second stage of preparatory works: levelling of the site, construction site infrastructure, preparation for concrete batching plants and water, sewage and electrical networks. PEJ
  • 24 June change dateu The Ministry of Energy published the full text of the updated Polish Nuclear Power Programme: first concrete in 2028, operation of the units in 2036, 2037 and 2038 (against 2033, 2035 and 2037 in the 2020 programme), 40% local content at the first unit. The document awaits a resolution of the Council of Ministers. Ministerstwo Energii
  • 25 June date Marek Woszczyk, President of PEJ: “We are holding to pouring the first concrete in 2028. But even if this happens in early 2029” - with no effect on the 2036 commissioning date. President of PEJ w rozmowie z forsal.pl
  • 17 June change dateu The target for closing EPC contract negotiations moved from 30 June 2026 to autumn 2026. Westinghouse maintained that pouring the first concrete in Q4 2028 remains the goal. Parkiet
  • 12 June date The Ministry of Energy presented the outline of the Programme update: the first reactor of the first plant in 2036; the second plant - first reactor in 2040, selection of a strategic partner and technology, with Bełchatów or Konin under consideration as locations. Ministerstwo Energii
  • 20 May fact PEJ and Statistics Poland signed an agreement on cooperation in measuring local content. PEJ
  • 19 May date The president of PEJ: the intention to sign the EPC contract by the end of the year; operation of the units in 2036 - 2038. President of PEJ w rozmowie z wnp.pl
  • 8 May fact PEJ received the opinion of the President of PAA on the nuclear safety of the plant site. PEJ / PAA
  • 23 April fact ZBUD of Dąbrowa Tarnowska began the process of adapting to ASME NQA-1 as the seventh Polish company in the qualification programme. PEJ
  • 10 April change The Ministry of State Assets announced a definition of local content based on six weighted criteria: parent company seat in Poland (25%), core activity in Poland (25%), tax residence (15%), more than half of employees being Polish citizens or residents (15%), registration and a minimum of three years of activity (10%), more than half of revenue generated in Poland (10%). Parkiet
  • 31 March fact PEJ filed an application with the President of PAA for a licence to build the plant - more than 40,000 pages of documentation. The statutory deadline for a decision is 24 months. From the announcement: first concrete in Q4 2028, application for a building permit in 2027, start-up in 2036. PEJ
  • 25 March fact The president of PEJ: the government uses an indicative local content figure of 40%; PEJ have signed more than 400 contracts with domestic companies worth more than PLN 1 billion. President of PEJ w rozmowie ze stockwatch.pl
  • 19 - 20 March fact Baltic Nuclear Energy Forum 2026 in Gdańsk - the programme included a session on the business ecosystem and the supply chain. BNEF
  • 4 March fact PEJ conference “Atomowe Szanse” in Gdańsk: quality standards and certification procedures, planned contracts, consultations for companies. PEJ
  • February fact Bechtel signed a contract with the Gdańsk company DORACO to support the phase 2 and 3 geological and geotechnical investigations, including the construction of 13 drilling platforms; the works are due to be completed in Q2 2027. Gospodarka Morska
  • 11 February fact Westinghouse: 6 Polish companies have been through the QA-1 standards process, mainly in steel structures; the first long-lead components ordered are the turbines and generators. Westinghouse Polska
  • 30 January fact PEJ signed their first loan agreement with US EXIM under the Engineering Multiplier Program; EXIM had previously issued a letter of interest for USD 17.8 billion. PEJ
  • 13 January fact Bechtel and Westinghouse selected Arabelle Solutions as supplier of three sets of steam turbines and generators for all three units. Production is to start once the EPC contract is finalised. PEJ / Bechtel
2025
  • 30 December fact PEJ received the first tranche of the capital injection - treasury bonds worth PLN 4.6 billion. Wojewoda Pomorski
  • 29 December fact PEJ and the Westinghouse - Bechtel consortium signed an annex to the EDA: continuation of design work, deeper geological investigations, purchases of long-lead components. PEJ
  • 9 December fact The European Commission approved State aid for the project: a capital injection covering about 30% of project costs, State Treasury guarantees on 100% of the debt raised and a two-way contract for difference for 40 years. Estimated capital expenditure: about EUR 42 billion (PLN 178 billion) in nominal terms. Komisja Europejska
  • 3 September fact ZKS Ferrum and Mostostal Kielce completed the first stage of qualification. PEJ then publicly described the structure of the three stages: procedures, implementation and training, manufacture of a trial component. PEJ
  • 18 August fact The Office of Technical Inspection (UDT) began agreeing the documentation of equipment for the plant - reactor vessels, steam generators, primary and secondary circuit equipment and auxiliary systems in AP1000 technology. PEJ
  • August fact The Pomeranian Voivode issued a decision permitting preparatory works to begin - stage one. Wojewoda Pomorski
  • 31 July fact FAMAK and Mostostal Kraków completed the first stage of conformity with ASME NQA-1 - drawing up procedures in 18 areas, including quality assurance, control of equipment, design and documentation, and corrective action. PEJ
  • 10 - 11 June fact The 8th Supplier Day in Sopot - about 100 Polish companies, nearly half of them from Pomerania. PEJ
  • 28 April fact PEJ and the Westinghouse - Bechtel consortium signed a nine-month Engineering Development Agreement (EDA), replacing the earlier ESC agreement. PEJ
  • 11 April fact The act on the capital injection into PEJ entered into force. ISAP - Dz.U. 2025 poz. 393
  • 27 March date Government plenipotentiary Wojciech Wrochna: first concrete on the construction site in 2028, start of commercial operation in 2036. Government plenipotentiary in an interview with wnp.pl
  • 25 March fact The President of Poland signed the act on a capital injection into PEJ of up to PLN 60.2 billion for 2025 - 2030; release of the funds was conditional on European Commission approval. Bankier.pl
  • 20 February fact The Sejm passed the act on the capital injection into PEJ. ISAP - Dz.U. 2025 poz. 393
2024
  • 18 December fact The European Commission opened a formal investigation into Polish State support for the project. Komisja Europejska
  • 11 December change dateu Government plenipotentiary Wojciech Wrochna: the Programme update provides for commercial operation of the first unit to begin in 2036, and of the second and third units in 2037 and 2038; building permit and start of works in 2028. The previous dates were 2033, 2035 and 2037. Government plenipotentiary in an interview with bankier.pl
  • December fact UDT issued the first decision permitting the manufacture of equipment for this plant - for the Italian Westinghouse Mangiarotti works. PEJ
  • 15 November fact Westinghouse placed its first orders with Polish suppliers: implementation of quality assurance systems, nuclear safety culture standards, preparation of documentation and potential manufacture of components for AP1000 structural modules. Westinghouse Polska
  • September fact Poland notified the European Commission of the planned State aid for the project. Komisja Europejska - SA.109707
  • 24 June fact The Council of Ministers adopted resolution no. 66 amending the resolution on the update of the Polish Nuclear Power Programme. M.P. 2024 poz. 569
  • June fact A three-day Westinghouse technical workshop in Warsaw for selected suppliers: quality assurance to ASME NQA-1, AP1000 modular engineering and manufacture, project management. Westinghouse
  • 9 April fact Westinghouse announced the selection of seven Polish suppliers for nuclear island equipment, basing the decision on quality assurance standards. Westinghouse
2023
  • 26 October fact The Pomeranian Voivode issued the decision establishing the location of the investment: 3 AP1000 reactors with a total capacity of 3,750 MWe in the Choczewo commune. PEJ
  • 24 October fact PEJ, Westinghouse and Bechtel organised the first Supplier Day for companies from Pomerania. PEJ
  • 27 September fact PEJ and the Westinghouse - Bechtel consortium signed the ESC contract for the design of the plant: nuclear island, turbine island and accompanying installations; about 2 million man-hours over 18 months. PEJ
  • 11 July fact The Minister of Climate and Environment issued the decision in principle for PEJ to build the plant in AP1000 technology: 3 power units with a total capacity of up to 3,750 MWe. Ministry of Climate and Environment
  • 22 February fact PEJ and Westinghouse signed a bridge agreement covering the investment delivery model, the safety assessment and quality control programme, preliminary engineering work and the identification of suppliers. Ministry of Climate and Environment
2020 - 2022
  • 2 November 2022 fact The Council of Ministers adopted a resolution selecting Westinghouse’s AP1000 technology for the first plant: 3 power units with a total capacity of up to 3,750 MWe. From the announcement: start of construction in 2026, completion in 2033. Council of Ministers
  • 22 December 2021 fact PEJ indicated the preferred location: Lubiatowo-Kopalino in the Choczewo commune. Polski Atom, gov.pl
  • 15 June 2021 fact PGE EJ 1 changed its name to Polskie Elektrownie Jądrowe sp. z o.o. PEJ
  • 26 March 2021 fact The State Treasury bought back 100% of the shares in the company for about PLN 531 million. Nuclear.pl
  • 2 October 2020 date The Council of Ministers adopted the update of the Polish Nuclear Power Programme: start of construction of the first plant in 2026, commercial operation of the three units in 2033, 2035 and 2037. M.P. 2020 poz. 946

Plan versus reality

The table below sets out every publicly announced date in the order in which it was given.

Date of statementSource of statementUnit 1Units 2 and 3Start of constructionFirst nuclear concrete
24 June 2026Ministry of Energy, Programme update20362037 · 2038 -2028
25 June 2026President of PEJ20362037 · 2038 -2028 or early 2029
31 March 2026PEJ, application to the Atomic Energy Agency2036 - -Q4 2028
27 March 2025Ministry of Industry2036 - -2028
11 December 2024Government plenipotentiary20362037 · 2038works from 2028 -
2 November 2022Council of Ministers, choice of technology2033 -2026 -
2 October 2020Council of Ministers, Programme20332035 · 20372026 -

The table can be scrolled sideways.

The last two columns are 2 different events.

Start of construction - the start of works on the site.

First concrete - pouring the base slab of the nuclear island, the formal moment from which construction of a unit is counted.

Up to 2022 the announcements gave the date of the start of construction; from 2025 they use the first-concrete date. An empty cell means that the statement in question did not contain that date.

The questions asked most often

Is a nuclear power plant in Poland already being built?

Yes - preparatory works are under way on the site. The Pomeranian Voivode permitted their first stage in August 2025, and on 1 July 2026 the second: site levelling, construction-site infrastructure and concrete batching plants (PEJ).

Construction of the unit itself, however, counts only from the first concrete, scheduled for 2028. The EPC contract with the contractors’ consortium has still not been signed; the government declares that negotiations will be finalised by the end of 2026 (Senat RP, 22 July 2026).

When will the nuclear power plant in Poland start operating?

2036, 2037 and 2038 - units one, two and three respectively. This follows from the updated Polish Nuclear Power Programme, the full text of which the Ministry of Energy published on 24 June 2026 (Ministerstwo Energii).

In the programme adopted in 2020 the same units were to start up in 2033, 2035 and 2037 (M.P. 2020 poz. 946).

Where in Poland is the nuclear power plant being built? Location map

Lubiatowo-Kopalino, Choczewo commune, Wejherowo county, Pomeranian Voivodeship - on the Baltic coast, a few dozen kilometres from Gdańsk.

PEJ indicated the preferred location on 22 December 2021, and the Pomeranian Voivode issued the decision establishing the location of the investment on 26 October 2023 (PEJ). The location map is higher up on this page.

How many units will there be and what will the plant’s capacity be?

3 power units of about 1,250 MWe gross each - up to 3,750 MWe in total. This capacity is given in the Council of Ministers’ resolution of 2 November 2022, by which the AP1000 technology was selected (Council of Ministers).

According to PEJ, the 3 units will cover the demand of more than 12 million households (PEJ).

What does it cost and who pays for it?

About EUR 42 billion, or PLN 178 billion of capital expenditure. This figure was given by the European Commission when it approved Poland’s State aid for the project on 9 December 2025 (Komisja Europejska, IP/25/2963).

The support comprises a capital injection covering close to 30% of project costs, guarantees on 100% of the debt and a contract for difference for 40 years. The act on a capital injection into PEJ of up to PLN 60.2 billion for 2025 - 2030 entered into force on 11 April 2025, and the company received the first tranche - treasury bonds worth PLN 4.6 billion - on 30 December 2025.

Who is building it?

The Westinghouse and Bechtel consortium, in American AP1000 technology. The investor is Polskie Elektrownie Jądrowe, wholly owned by the State Treasury.

The AP1000 is a generation III+ pressurised water reactor designed by the American company Westinghouse. Until the EPC contract is signed, the parties are working under the EDA agreement of 28 April 2025, extended by an annex of 29 December 2025 to cover further design work, geological investigations and the purchase of long-lead items (PEJ).

Is a plant like this already operating anywhere?

Yes - 6 AP1000 units are in commercial operation. 4 in China, at the Sanmen and Haiyang plants, commissioned in 2018 - 2019, and 2 in the United States, at the Vogtle plant in Georgia: unit 3 since July 2023 and unit 4 since April 2024 (NucNet, April 2026).

This is the same design that is to be built at Lubiatowo-Kopalino. Westinghouse states that a further 14 AP1000 units are under construction in China and 5 more have been contracted (Westinghouse). The Polish units will therefore not be the first of their kind - the design has more than a decade of operating experience behind it.

Who oversees nuclear safety?

The Polish National Atomic Energy Agency (PAA) - an authority independent of the investor, with its own inspection apparatus. It is the Agency that assesses the project documentation and it is the Agency that issues the licence to build a nuclear facility.

PEJ submitted the application on 31 March 2026, the documentation runs to over 40,000 pages, and the statutory deadline for the decision is 24 months - expiring in March 2028 (PEJ). Earlier, on 8 May 2026, the company received the Agency’s opinion on the nuclear safety of the site itself.

Who authorises plants to manufacture equipment for a nuclear power plant?

The Office of Technical Inspection (UDT) - but the requirement applies only to equipment important to nuclear safety. The Council of Ministers regulation of 17 December 2013 (Journal of Laws 2014, item 111) names it: the reactor containment system, the reactor cooling circuit together with auxiliary systems, the feedwater system, active and passive safety systems including emergency core cooling and residual heat removal. Conventional equipment, from the turbine island for example, follows the ordinary EU conformity assessment route with CE marking.

A plant that wishes to manufacture the former must first obtain an authorisation from UDT - an administrative decision issued under the Technical Inspection Act (UDT). The equipment itself may only be produced on the basis of documentation agreed with the Office. In this project UDT issued the first manufacturing authorisation in December 2024, for the Italian Westinghouse Mangiarotti plant, and began agreeing the AP1000 equipment documentation in August 2025 (PEJ).

How much of this will Polish companies do? What is local content?

40% at the first unit. Local content is the share of Polish suppliers in the value of the investment, and that is the level assumed by the updated Polish Nuclear Power Programme.

The President of PEJ stated on 25 March 2026 that more than 400 contracts had already been concluded with domestic companies, worth over one billion zloty (President of PEJ w rozmowie ze stockwatch.pl).

Does Poland already have a nuclear power plant? What about Żarnowiec?

No - no nuclear power plant has ever been completed in Poland. Construction of the plant on Lake Żarnowieckie, based on Soviet WWER-440 reactors, was carried out in the 1980s, and on 17 December 1990 the government of Tadeusz Mazowiecki adopted a resolution placing the investment in liquidation (Polski Atom, gov.pl). Żarnowiec and Lubiatowo-Kopalino lie in the same Wejherowo county, and Żarnowiec was the second location studied in 2017 - 2021.

The only nuclear reactor operating in Poland today is the MARIA research reactor at Otwock-Świerk, running since 1974. It produces radioisotopes for medicine and serves research - it does not generate electricity (Polski Atom, gov.pl).

Will there be a second nuclear power plant in Poland?

Planned for 2040, at Bełchatów or Konin. This was indicated by the Ministry of Energy when it presented the outline of the programme update on 12 June 2026 (Ministerstwo Energii). This page concerns only the first investment.

And what about small modular reactors?

A separate programme, a different investor and a different technology. The first plant with small modular reactors is planned by Orlen Synthos Green Energy in BWRX-300 technology, with Włocławek as the preferred location; start-up is declared for the early 2030s.

On 24 February 2026 in Washington the company signed an agreement with GE Vernova Hitachi to develop a Polish version of the reactor design - adapted to Polish regulations, safety requirements and environmental conditions (Ministerstwo Energii). SMRs and the plant at Lubiatowo-Kopalino are 2 independent undertakings and should not be confused.

Sources

This page is based on material from: Polskie Elektrownie Jądrowe, Ministerstwo Energii, Pomorski Urząd Wojewódzki, Państwowa Agencja Atomistyki, Komisja Europejska, Westinghouse Polska, Bechtel, ISAP. Each entry is signed with the source it links to: a document or an institution’s statement, and where there is no official record - a remark reported in the media, in the form “institution via outlet”.

How I keep this page

I publish publicly announced information, with the source and date indicated. Changed dates stay visible next to the new ones - so both the current schedule and its history can be seen.

This timeline is kept by Dzmitry Keura, Keura Nuclear. First published: 5 August 2026. If you have spotted an error or a missing event with a link to its source - write to me and I will correct it.

Przedruk dozwolony - w całości, bez zmian, ze wskazaniem źródła. Szczegóły.

Reprinting permitted - in full, unchanged, with the source indicated. Details.

Перепечатка разрешена - целиком, без изменений, со ссылкой на источник. Подробнее.

Scroll to Top